AGC Supervisory Training Program
Issued by: Associated General Contractors of America (AGC)
Supervisory skills, scheduling, cost control, and communication fundamentals from the AGC's widely recognized training curriculum.
Exam blueprint
Sourced from AGC Supervisory Training Program (STP) Curriculum — current edition (six units)
- Unit 1: Leadership + Motivation15%
- Unit 2: Communication15%
- Unit 3: Planning + Scheduling (CPM basics)20%
- Unit 4: Contract Documents + Construction Law (basics)15%
- Unit 5: Improving Productivity + Managing Costs20%
- Unit 6: Risk Management + Problem-Solving15%
Study modules
5 modules · 11 questions01Unit 1: Leadership and Motivation — leading a working crew
~90minField supervision is operational leadership under time pressure. STP Unit 1 teaches the practical leadership skills every foreman and superintendent uses daily — situational leadership, motivation theory, conflict, and discipline.
Situational leadership — match style to follower readiness
Hersey-Blanchard situational leadership is the conceptual backbone of STP Unit 1. Four leadership styles map to four levels of follower competence + commitment: (1) DIRECTING — high task / low relationship — for new workers who don't yet know the work; supervisor specifies what + how + when. (2) COACHING — high task / high relationship — for workers building skill; supervisor still directs but explains why and seeks input. (3) SUPPORTING — low task / high relationship — for skilled workers losing motivation; supervisor focuses on encouragement + obstacle removal. (4) DELEGATING — low task / low relationship — for fully competent + committed workers; supervisor sets the goal and gets out of the way. The KEY MISTAKE field supervisors make: applying ONE style (often Directing or Delegating) to everyone. STP teaches reading the worker's readiness for the specific TASK at hand and adjusting style — the same worker may be 'D4 delegated' on framing and 'D1 directed' on a new layout method.
Motivation theory + practical levers in field environments
STP introduces the motivation theory landscape briefly: Maslow's hierarchy, Herzberg's hygiene-vs-motivator distinction, McGregor Theory X/Y. The practical takeaway for a working foreman: HYGIENE FACTORS (pay, safety, working conditions, perceived fairness) cause DISSATISFACTION when absent but do not motivate when present. MOTIVATORS (achievement, recognition, growth, responsibility) actually drive engagement. A foreman who fixes a hygiene complaint (e.g., proper PPE, better break schedule) removes a dissatisfaction source but doesn't suddenly create motivation. To motivate: assign challenging-but-achievable work, give specific recognition for good work (in front of peers when possible), explain the WHY of decisions, and create growth opportunities (cross-train workers on the next-skill-up trade). STP-trained supervisors can name 5-6 specific motivators applicable to their crew — that's the unit's practical bar.
Progressive discipline + documentation
STP teaches the union-and-non-union-friendly progressive discipline model: (1) VERBAL warning — documented in the supervisor's notes; specific behavior, expected change, deadline. (2) WRITTEN warning — same content in writing, signed by supervisor and worker (worker signature acknowledges receipt, not agreement); copy to HR. (3) FINAL WARNING / SUSPENSION — clear notice that the next incident leads to termination; HR involvement mandatory. (4) TERMINATION — coordinated with HR + legal review. SAFETY VIOLATIONS often skip steps — a refusal to wear fall protection at height is typically immediate suspension, not verbal warning. Documentation matters: an undocumented progressive-discipline path is no path at all when a worker is terminated and grieves the action. STP teaches the WRITE-IT-DOWN reflex — every conversation with a performance dimension goes into the supervisor's notes that day.
Practice questions (2)
1. A skilled veteran carpenter on your crew has been showing up late and producing inconsistent work for the last two weeks. Per situational leadership, the most appropriate style for this worker right now is:
Pick an answer to see the explanation.
2. A field supervisor has a series of performance conversations with a struggling apprentice over six weeks but documents none of them. The apprentice is later terminated and grieves the termination. Most likely outcome of the grievance?
Pick an answer to see the explanation.
02Unit 2: Communication — the supervisor as information hub
~75minField supervisors transmit information up, down, and sideways constantly. STP Unit 2 builds active-listening skills, written communication discipline, and the ability to run a productive crew meeting.
Active listening + the listening trap
STP teaches active listening as a four-step practice: (1) ATTEND — face the speaker, eye contact, no phone; (2) PARAPHRASE — restate what you heard ('So you're saying the rebar shipment is short by 200 feet — is that right?'); (3) CLARIFY — ask one or two specific follow-up questions; (4) RESPOND — only after understanding is confirmed. The LISTENING TRAP that catches new supervisors: planning your response while the other person is still talking. The cure is paraphrasing — you can't paraphrase if you weren't actually listening. Field application: an experienced super, when a foreman brings a problem, takes 30-60 seconds to listen and paraphrase before offering any solution. This builds trust AND surfaces information the foreman might withhold from a fast-talking boss.
Written communication — daily reports + email discipline
Field supervisors write more than they realize: daily reports, RFI text, deficiency notices, change-order narratives, email to office. STP teaches the BLUF principle — Bottom Line Up Front. The reader should know in the first sentence what you are asking, telling, or warning. Bury the lead and the reader skims past it. For DAILY REPORTS specifically: factual + dated + signed. No interpretation, no blame. 'The mason crew was held up 4 hours waiting for the brick delivery; reroute attempted to other elevations.' Not: 'The brick supplier always screws us.' For EMAIL: use subject lines that signal action ('Action needed by Friday: column placement decision'); keep to one topic; use bulleted lists for readability. Most office-side conflict between project teams comes from poorly-written field communication that is interpreted as accusatory.
Running a productive crew + coordination meeting
Two meeting types every supervisor runs: (1) DAILY HUDDLE / TOOLBOX TALK with the crew — 5-10 minutes, stand-up, before work starts. Cover: today's plan + safety hot-spot + any change from yesterday + handoff coordination. End with one concrete safety reminder. STP-trained supervisors run a tight huddle that crews actually appreciate. (2) WEEKLY COORDINATION MEETING with foremen + super + sub PMs — 30-60 minutes. Agenda items: (a) safety review; (b) schedule check — what's behind, what's the recovery plan; (c) coordination handoffs (who is in whose way next week); (d) RFIs / submittals waiting on action; (e) one-week look-ahead. Keep notes; close the loop on action items at the next meeting. The cardinal sin: a meeting that runs long, has no agenda, and ends with no documented action items. STP teaches that meeting discipline is a measurable supervisor competency.
Practice questions (2)
1. A foreman reports to you (the super) that the concrete sub is consistently late to the morning crew brief. The BEST opening response per active-listening practice is:
Pick an answer to see the explanation.
2. Best practice for the weekly coordination meeting per STP Unit 2:
Pick an answer to see the explanation.
03Unit 3: Planning + Scheduling — CPM at the field-supervisor level
~105minField supervisors don't typically build the master CPM, but they live inside it. STP Unit 3 teaches the supervisor to read the schedule, identify their critical-path activities, manage float, and update the schedule weekly with reliable look-aheads.
CPM basics — activity, predecessor, duration, critical path
Critical Path Method represents the project as a NETWORK of activities (boxes) connected by relationships (arrows showing predecessors). Each activity has a duration, an early start (ES), early finish (EF), late start (LS), late finish (LF), and total float (LS − ES, equivalently LF − EF). The CRITICAL PATH is the longest chain through the network — its activities have ZERO total float. Any delay on a critical-path activity slips the project end-date one-for-one. Activities OFF the critical path have float — slack time before they impact the project. STP-trained supervisors know which of THEIR activities are on the critical path and which have float. The four relationship types: FINISH-TO-START (FS) — most common, predecessor finishes before successor starts; START-TO-START (SS); FINISH-TO-FINISH (FF); START-TO-FINISH (SF, rarely used). LAGS shift relationships in time (FS+5 = predecessor finishes, then 5 days, then successor starts — typical for concrete cure time).
Three-week look-ahead — the supervisor's weekly tool
The MASTER schedule is built once and updated periodically. The THREE-WEEK LOOK-AHEAD is the supervisor's WORKING tool, refreshed every week. It shows in detail: the past week (actuals vs. plan), the current week (commitments + handoffs), and the next two weeks (planned activities with named crews + materials + equipment + predecessor confirmations). The look-ahead is the basis for the weekly coordination meeting. STP teaches the discipline of CONFIRMING look-ahead activities with the foremen who will run them — 'will you be ready to start the framing on Tuesday?' If the answer is 'no, the slab is not cured' the look-ahead changes BEFORE the week starts, not after a missed handoff. The look-ahead is the mechanism by which big-CPM-thinking gets turned into daily field reality.
Schedule recovery — when you slip, what do you do?
When the project slips on a critical-path activity, the supervisor's options: (1) ABSORB — if there is downstream float that can absorb the slip without slipping the project end. Cheap, but consumes future flexibility. (2) FAST-TRACK — overlap currently-sequential work (start framing while final slabs are still curing in another area). Risk: rework if the predecessor changes. (3) CRASH — add resources to shorten activity duration. Costs go up; productivity per added person drops as crowding increases (the law of diminishing returns kicks in around 1.25× the planned crew size). (4) RE-SEQUENCE — change activity order if logically possible (rare on most projects). (5) ACCEPT THE SLIP — if recovery is more expensive than the slip itself. STP teaches the supervisor to PRESENT THE OPTIONS to the project manager with cost + risk + benefit, not just request the schedule be changed.
Practice questions (2)
1. On a project with 12-month duration, a critical-path activity has 10 days of total float. What can you conclude?
Pick an answer to see the explanation.
2. You are a superintendent on Friday afternoon. Your three-week look-ahead shows framing starts Tuesday. What is the STP-disciplined action right now?
Pick an answer to see the explanation.
04Unit 4: Contract Documents + Construction Law (basics)
~75minField supervisors don't draft contracts but they LIVE in them. STP Unit 4 builds working knowledge of the contract document hierarchy, change-order process at the field level, and basic construction law concepts (warranty, liens, indemnification).
The contract document hierarchy + finding the right answer
Standard private-sector hierarchy (AIA-style): (1) the AGREEMENT (signed contract); (2) GENERAL CONDITIONS (e.g., AIA A201); (3) SUPPLEMENTARY CONDITIONS (project-specific overlays to A201); (4) SPECIFICATIONS; (5) DRAWINGS; (6) ADDENDA + APPROVED MODIFICATIONS. When documents conflict, the higher-tier document typically controls — but the actual conflict resolution clause IS in the contract and may invert the order (e.g., on federal jobs the SPEC controls over the DRAWING — the opposite of common private practice). STP teaches the supervisor to KNOW WHERE TO LOOK rather than memorize: spec section for material + workmanship requirements; drawings for geometry + dimensions; general conditions for change-order process + payment + warranty. The supervisor who can find the answer in the contract within 5 minutes is twice as effective as one who guesses.
Field-directed change vs. proper change order
A common foreman + super trap: an owner's representative or designer says in passing 'just go ahead and add another receptacle here.' The field crew does it. Six weeks later the owner refuses to pay because there's no signed change order. STP teaches the WRITTEN-DIRECTION rule: any work outside the contract scope requires WRITTEN authorization through the contract's change-order process before performing the work. If schedule pressure won't allow waiting, the appropriate vehicle is a CONSTRUCTION CHANGE DIRECTIVE (CCD) — owner's WRITTEN unilateral direction to proceed; cost reconciled later. Verbal direction from anyone who isn't the contracting officer / owner's authorized representative is not a basis to proceed. The supervisor's discipline: 'I'll get this done as soon as I have written direction' — every time, even when uncomfortable.
Basic construction law concepts every supervisor should know
STP introduces (does NOT make experts of supervisors in) five concepts: (1) WARRANTY — contractually-defined period during which the contractor is on the hook for defects (typically 1 year correction period for workmanship; longer for some materials). The supervisor's role: capture punch-list items and follow-up corrections diligently, because warranty calls track back to documented corrections. (2) LIEN RIGHTS — most state laws give contractors and subs the right to file a mechanic's lien on the property if not paid; deadline-driven (typically 60-120 days from last work). (3) INDEMNIFICATION — clauses where one party agrees to defend / cover claims against another. Scope varies — supervisors don't draft these but recognize them in subcontract review. (4) DIFFERING SITE CONDITIONS — Type I (conditions differ from contract documents) and Type II (unusually difficult conditions); both require WRITTEN NOTICE within contract-specified time, often 7-10 days. (5) STATUTE OF LIMITATIONS / REPOSE — there is a final cutoff after which claims cannot be brought, varying by state.
Practice questions (2)
1. On a private AIA-form project, the SPECIFICATION says use Type X gypsum board; the DRAWING says use Type C. Per typical AIA hierarchy, which controls?
Pick an answer to see the explanation.
2. An owner walks the site and verbally tells the foreman to add a window in a wall that isn't in the drawings. STP-disciplined response?
Pick an answer to see the explanation.
05Unit 5 + 6: Productivity, Cost, Risk, Problem-Solving
~120minThe last two STP units cover the supervisor's role in measuring + improving productivity, controlling project costs at the field level, identifying and managing risk proactively, and structured problem-solving when things go sideways.
Measuring and improving productivity — units per labor hour
Productivity is measured as UNITS OF OUTPUT per UNIT OF LABOR INPUT — typically 'productivity factor' (PF) = budgeted labor hours / actual labor hours. PF > 1.0 = beating budget. PF < 1.0 = behind. STP teaches the supervisor to TRACK productivity by activity (e.g., linear feet of conduit per electrician-hour) rather than just total labor cost. When productivity drops, the cause is usually one of the FIVE FRICTIONS: (1) materials not staged where needed; (2) tools / equipment not available; (3) preceding work incomplete; (4) crew composition wrong (too many apprentices, missing journeyman); (5) information missing (unclear drawings, RFI not answered). The supervisor's job is to walk the work, identify which friction is biting today, and remove it. Twenty percent of productivity loss is fixable in real-time by an attentive super; the rest requires schedule + sequencing changes.
Field cost control — labor budgets, equipment hours, waste
The field supervisor controls three cost categories directly: (1) LABOR — by managing crew size + composition + productivity. STP teaches reading the labor budget per activity, knowing your hours-spent vs. budget weekly, and flagging variances early. (2) EQUIPMENT — by minimizing IDLE TIME (rented backhoe sitting unused while crew waits on inspection = full hourly cost burning cash). Coordinate equipment delivery + return tightly with planned use. (3) MATERIAL WASTE — track delivery quantity vs. installed quantity per major material; cull orders that systematically over-arrive. STP-trained supervisors review their LABOR REPORT weekly and can name two to three activities with productivity issues at any time — that's the operating bar.
Risk management at the field level — identify, assess, control
STP teaches a simplified risk framework appropriate for the field: (1) IDENTIFY — what could go wrong this week / this phase? Walk the site with risk-spotting eyes (weather forecast, equipment age, new crew, unfamiliar method, lookahead). (2) ASSESS — likelihood × impact. High-likelihood high-impact = act now. Low-likelihood high-impact = mitigate (insurance, contingency plan). Low-likelihood low-impact = accept. (3) CONTROL — engineering controls > administrative controls > PPE (in safety risks); for schedule + cost risks: contingency days/dollars, alternative supplier, cross-trained crew. (4) MONITOR — review weekly. The supervisor's habit: keep a running TOP-FIVE-RISKS list for the project and revisit it at every coordination meeting. The unsexy 'risk register' habit catches more incidents than the sexiest hard-hat.
Structured problem-solving — root cause + 5-Whys
When a problem hits (failed inspection, missed pour, defective material), STP teaches structured problem-solving rather than blame: (1) STATE THE PROBLEM in measurable terms ('the second-floor slab failed compressive strength testing — 3,200 psi vs. 4,000 psi required'). (2) GATHER FACTS — what was the mix, who placed it, what was the temperature, what was the cure protocol. (3) 5-WHYS — ask why five times to drive past symptom to root cause ('why did it fail compression? Low water-cement ratio at delivery. Why? Truck driver added water on arrival. Why? Concrete was stiff in chute. Why? Truck waited 45 min after batching. Why? Pump truck was late'). (4) CORRECTIVE ACTION at the root cause ('schedule pump truck and concrete delivery to overlap at site'). (5) PREVENTIVE ACTION ('add this coordination check to the preparatory phase checklist for all future pours'). The 5-Whys habit prevents recurrence; just-fix-the-symptom guarantees recurrence.
Practice questions (3)
1. A foreman reports that a conduit-installation crew is producing 60 feet per labor hour vs. budgeted 80 feet per labor hour (PF = 0.75). The MOST useful first action per STP Unit 5?
Pick an answer to see the explanation.
2. A super walks the site Monday and notices the only operational concrete pump is showing oil-pressure warnings. Per STP Unit 6 risk practice, the most disciplined response is:
Pick an answer to see the explanation.
3. A pour fails compression strength tests. The supervisor uses 5-Whys and traces the cause to a 45-minute wait between batching and placement. The most useful CORRECTIVE + PREVENTIVE action per STP problem-solving practice?
Pick an answer to see the explanation.
External resources
- OfficialAGC Supervisory Training Program — official curriculum portal ↗
AGC's official STP page with unit descriptions, instructor materials, and a chapter locator. Most local AGC chapters offer all six units on a rolling 12-18 month cadence — find the chapter offering the next unit start.
- OfficialAGC Education and Training Resources — Field Supervisor Library ↗
AGC's broader training library — STP is the flagship but related resources (BIM for field supervisors, Lean Construction Education Program LCEP, Project Manager Development Program PMDP) round out a supervisor's path. Read alongside STP material to see how the AGC curriculum maps to the field-supervisor career arc.
- Third-party29 CFR 1926 Subpart C — General Safety + Health Provisions ↗
Subpart C is the OSHA construction-industry section every field supervisor must operate inside. STP Units 1 + 6 reference safety responsibilities throughout — knowing the actual regulation makes the STP guidance concrete instead of abstract.
Last updated: 2026-04-27
This catalog card is not marked Ready yet
You can study the modules above. Leave an email if you want a note when this card is marked Ready.
