All credentials
SpecialtyIn progressWelding

AWS D1.5 Bridge Welding

Issued by: American Welding Society (AWS)

Specialized prep for the D1.5 Bridge Welding Code, including fracture-critical requirements, preheat controls, and AASHTO provisions.

40 hours typical prep time|Modules on this page

Exam blueprint

Sourced from AWS D1.5/D1.5M:2020 — Bridge Welding Code (jointly with AASHTO)

  • Scope + key differences from D1.110%
  • Charpy V-Notch (CVN) impact testing of qualification20%
  • Fracture-Critical Members (FCM) — Clause 1220%
  • NDT — RT/UT requirements for bridge welds20%
  • Preheat, interpass, and hydrogen control10%
  • AWS QC1 inspection requirements + CWI role10%
  • ANSI/AASHTO/AWS welder qualification chain10%

Study modules

5 modules · 8 questions
  1. 01D1.5 vs D1.1 — what changes for bridge work

    ~60min

    D1.5 inherits much of D1.1 but adds bridge-specific provisions because bridges experience cyclic loading, are often non-redundant, and carry public traffic. Knowing where the codes diverge is the test (and the field) discriminator.

    • Who has jurisdiction — AASHTO + state DOT

      D1.5 is invoked by reference in AASHTO's LRFD Bridge Construction Specifications. Every state Department of Transportation (DOT) adopts D1.5 (or a modified version) for state-highway bridges, federal-aid bridges, and most municipal arterial bridges. Private structures (a parking-deck pedestrian bridge in a private development) may default to D1.1 instead. The first question on any bridge job is: "Whose code applies?" The answer is usually D1.5 PLUS a state DOT supplement (a "Special Provisions" document) that adds even tighter requirements specific to that DOT.

      Reference: AASHTO LRFD Bridge Construction Specifications Article 11 (Welded Construction)

    • Where D1.5 diverges from D1.1

      Major differences worth memorizing: (1) D1.5 requires CHARPY V-NOTCH (CVN) testing of weld qualification specimens; D1.1 generally does not. (2) D1.5 has a separate FRACTURE-CRITICAL MEMBER (FCM) plan in Clause 12 with its own additional requirements; D1.1 does not address FCM at all. (3) D1.5 requires 100% NDT (typically UT or RT) on tension members and CJP butt welds; D1.1 leaves NDT to the engineer. (4) D1.5 mandates AWS QC1-certified inspection (CWI required); D1.1 only RECOMMENDS it. (5) D1.5 has tighter preheat tables and stricter hydrogen-control requirements (low-hydrogen electrodes only, often with reconditioning protocols).

    Practice questions (1)
    1. 1. A fabricator is welding plate girders for a state-highway bridge. Which code primarily governs the welding?

      Pick an answer to see the explanation.

  2. 02Charpy V-Notch (CVN) impact testing

    ~75min

    Bridges experience low-temperature, dynamic loading. CVN testing measures the toughness of weld and HAZ — the resistance to brittle fracture at service temperature. D1.5 requires CVN tests of qualification specimens; D1.1 does not.

    • What CVN testing measures

      A Charpy V-Notch test takes a small machined specimen (10 × 10 × 55 mm with a precise notch) and breaks it with a calibrated pendulum at a specified test temperature. The energy absorbed during fracture (in foot-pounds or joules) is the CVN value. High value = ductile, tough material. Low value = brittle. Bridge steels are tested at the COLDEST service temperature the bridge will see. Three temperature zones in D1.5: Zone 1 (warmer states, 0°F minimum service temp), Zone 2 (moderate, -30°F), Zone 3 (cold, -60°F). The required CVN energy is given in tables that vary by zone, member type, and yield strength.

      Reference: AWS D1.5 Clause 5 + Annex IV (CVN procedures)

    • Where CVN specimens are taken

      D1.5 prescribes specific specimen locations within a procedure-qualification weld: in the WELD METAL itself, in the HEAT-AFFECTED ZONE (HAZ) at varying distances from the fusion line, and (for some applications) in the BASE METAL. Three specimens at each location, all tested at the same temperature, with both individual minimum and average minimum values required. A single specimen below the individual minimum can fail the entire WPS qualification. This is why bridge fabricators run multiple-specimen qualification panels and bank "test buttons" so a failed specimen does not cost weeks of re-qualification.

    • CVN values for FCM members

      Fracture-critical member (FCM) welds have HIGHER CVN requirements than non-FCM members in the same zone. A typical example from D1.5 Table 12.x: a non-FCM member in Zone 2 may require 20 ft-lb at -30°F, while the same member designated FCM might require 25 ft-lb at -30°F. The numbers vary by edition and steel grade — never quote from memory; always read the current table. The point: FCM toughness requirements are tighter precisely because failure of an FCM is, by definition, catastrophic.

    Practice questions (2)
    1. 1. A welder qualified under AWS D1.1 (no CVN testing performed) is asked to weld a tension flange on a state highway bridge plate girder. Action?

      Pick an answer to see the explanation.

    2. 2. During CVN testing of a D1.5 procedure-qualification weld, one of the three weld-metal specimens fails the individual minimum at -30°F. The other two pass, and the average exceeds the required average. Outcome?

      Pick an answer to see the explanation.

  3. 03Fracture-Critical Members (FCM) — Clause 12

    ~90min

    Clause 12 is the heart of D1.5's bridge-specific work. FCM members require dedicated quality, planning, and inspection. Fabricators need an AISC Sophisticated Paint Endorsement-tier QA program plus an additional FCM endorsement to fabricate FCMs.

    • What makes a member fracture-critical

      A FRACTURE-CRITICAL MEMBER (FCM) is a tension member or tension component of a member whose failure would result in COLLAPSE of the bridge — there is no load-redistribution path. Classic examples: tension flanges and tension diagonals on a two-girder bridge, eyebars on a pin-and-hanger truss, tension chords on a tied-arch tie. Bridge engineers identify FCMs on the design drawings and label them explicitly. Non-FCM members in the same bridge get standard D1.5 treatment; FCMs get Clause 12 treatment, which is materially more demanding.

      Reference: AWS D1.5 Clause 12.1 (FCM definitions)

    • The FCM Quality Plan

      A fabricator producing FCM components must maintain a written FCM Quality Plan covering: material control (CVN-tested plate, mill certs traced), welding procedures (FCM-specific WPSs with dedicated CVN-tested qualifications), welder qualifications (welders specifically qualified for FCM work and tracked individually), NDT (100% UT/RT, with technicians qualified per ASNT), and traceability of every weld back to a welder, electrode lot, and procedure. Most state DOTs require fabricators to hold an AISC certification with the SBR/FCM endorsement (Major Steel Bridge Fabricator, Fracture-Critical) to fabricate FCM components.

      Reference: AWS D1.5 Clause 12.4 (FCM fabrication plan)

    • FCM-specific welding restrictions

      Clause 12 imposes additional restrictions on FCM welding: (1) Tack welds must be made by qualified welders and inspected — not just by helpers. (2) Run-on / run-off tabs must be used on all CJP groove welds and removed by grinding (not torch-cut close to the joint). (3) Backing bars on T-joints are typically removed and the back gouged + back-welded. (4) Repair welding is restricted — multiple repairs at the same location may require engineer approval. (5) Stamping or hard-stamping of FCM material is generally prohibited (stress concentrators); identification uses paint or vibroetched marks.

    Practice questions (2)
    1. 1. A fabricator is welding the bottom-flange tension splice on a two-girder bridge designated as FCM by the engineer. Run-off tabs are torch-cut flush with the joint. Acceptable?

      Pick an answer to see the explanation.

    2. 2. On a tied-arch bridge, the tie plate carrying the horizontal thrust from the arch is identified by the engineer as fracture-critical. Compared to non-FCM welds on the same bridge, FCM welds require:

      Pick an answer to see the explanation.

  4. 04NDT + AWS QC1 inspection

    ~75min

    D1.5 mandates the volume of NDT D1.1 only recommends. Tension-member CJP butt welds typically get 100% RT or UT. All inspection must be performed under an AWS QC1-certified Quality Control program, with visual inspection by a CWI.

    • 100% NDT for tension members and CJP butts

      D1.5 requires 100% RADIOGRAPHIC TESTING (RT) or ULTRASONIC TESTING (UT) on all complete-joint-penetration (CJP) groove welds in tension members. Compression-member CJP welds typically get sample NDT (often 25% spot UT or RT). Fillet welds get 100% MAGNETIC PARTICLE (MT) on bridge work — much higher than D1.1's typical 10% sampling. The choice between RT and UT depends on access and material — UT is preferred for thick sections (>1.5 in) where RT becomes impractical, and for cracks (which UT detects more reliably than RT).

      Reference: AWS D1.5 Clause 6 (Inspection) + Table 6.x

    • NDT personnel qualification — ASNT SNT-TC-1A

      NDT technicians performing UT, RT, MT, or PT under D1.5 must be qualified to ASNT (American Society for Nondestructive Testing) SNT-TC-1A or CP-189, typically at LEVEL II (capable of performing testing and interpreting results independently). The NDT contractor maintains a written practice describing how they qualify and certify their technicians. This is more rigorous than D1.1 typically requires. Most state DOTs additionally require NDT contractors to be AISC NDT-certified or pre-approved on a state DOT roster.

    • AWS QC1 + the CWI requirement

      D1.5 mandates that VISUAL INSPECTION be performed by a Certified Welding Inspector (CWI) qualified per AWS QC1. D1.1 RECOMMENDS this; D1.5 REQUIRES it. The CWI inspects fit-up, before-welding conditions, in-process welding parameters, and final visual acceptance per Clause 6. A CWI signature is the gateway to NDT — failed visual inspections do not proceed to UT/RT. This is also why bridge contractors must factor CWI staffing into their bid: a fabrication shop turning out bridge girders typically needs a full-time on-staff CWI plus a third-party Quality Assurance (QA) inspector hired by the owner/engineer.

      Reference: AWS QC1 Standard for AWS Certification of Welding Inspectors

    Practice questions (2)
    1. 1. A 1-inch tension flange CJP butt weld on a state highway bridge girder must be NDT-tested per D1.5. Required coverage?

      Pick an answer to see the explanation.

    2. 2. Per AWS D1.5, who is required to perform the in-process visual inspection of bridge welds?

      Pick an answer to see the explanation.

  5. 05Welder qualification chain — ANSI/AASHTO/AWS

    ~60min

    Bridge welder qualification is a paper trail spanning three jurisdictions. Each layer adds requirements; missing any layer can void the welder's ability to deposit production weld on a state-DOT bridge job.

    • The three layers of qualification

      Layer 1 — D1.5 (AWS): the welder passes a procedure test (typically a 3G or 4G plate, or 6G pipe for pipe work) under a qualified WPS. CVN testing is performed on the procedure-qualification panels (not the welder-qualification panels). Layer 2 — AASHTO/AWS additional requirements: state DOTs frequently impose extra welder-qualification provisions (annual re-qualification, tracked welder logs, electrode-lot traceability). Layer 3 — Project-specific requirements: many DOTs maintain a list of pre-approved fabricators and individual welders. Even a properly qualified D1.5 welder may not be allowed on a particular state's bridge jobs without separate state-DOT pre-approval.

    • Maintaining qualification — the 6-month rule

      Once qualified, a welder must maintain CONTINUITY by depositing weld in the qualified process at least once every 6 months. Failure to weld for 6+ months requires re-qualification (in some cases, a re-test in just one position is sufficient; in others, a full re-test is required). Bridge fabricators track each welder's last weld date in the qualified process — usually with a barcode or stamp on each weld traced back to a daily log. Apprentice welders are often DOUBLE-tracked because their qualifications can be tied to a journeyman supervisor.

      Reference: AWS D1.5 Clause 5.27 (Period of Effectiveness)

    Practice questions (1)
    1. 1. A welder is qualified under AWS D1.5 in 3G plate position with FCAW process. They have not welded for 8 months. Are they qualified to start production welding tomorrow?

      Pick an answer to see the explanation.

External resources

  • Official
    AWS D1.5/D1.5M Bridge Welding Code ↗

    The actual code, jointly published by AWS and AASHTO. State DOTs adopt either the current edition or one a few cycles back — confirm which edition your project specifies BEFORE you study. Some clauses (especially Clause 12 FCM) have been substantially revised between editions.

  • Official
    AASHTO LRFD Bridge Construction Specifications ↗

    AASHTO's construction-side specification, which references D1.5 by section. Article 11 (Welded Construction) lays out where bridge construction sits in the broader AASHTO framework — useful context for inspectors and fabricators.

  • Third-party
    FHWA Manual on Inspection of Fracture-Critical Bridge Members ↗

    Federal Highway Administration guidance on FCM identification, inspection, and reporting. Particularly useful for understanding WHY D1.5 Clause 12 exists — failure modes and historical incidents that drove the FCM provisions are documented here.

Last updated: 2026-04-27

This catalog card is not marked Ready yet

You can study the modules above. Leave an email if you want a note when this card is marked Ready.

Free forever. No spam. Unsubscribe any time.