Master Electrician Exam Prep
Issued by: State Licensing Boards (varies)
Advanced NEC applications, service sizing, special occupancies, and business law topics tested on master electrician exams nationwide.
Exam blueprint
Sourced from NEC NFPA 70 (2023 edition) + Common State Master Electrician Exam Outlines (PSI/Prov/Block)
- NEC definitions + general requirements (Art. 100, 110)10%
- Wiring methods + overcurrent protection (Art. 240, 250, 300)15%
- Services + service sizing (Art. 230)12%
- Branch circuits + feeders (Art. 210, 215, 220)15%
- Grounding + bonding (Art. 250)13%
- Motors + motor circuit calculations (Art. 430)10%
- Special occupancies + locations (Art. 500-590, 700)10%
- Business + jurisdiction-specific law15%
Study modules
4 modules · 8 questions01Service entrance + service load calculations
~120minSizing the service is the single most common calculation question on the master exam. Standard vs. optional method, demand factors, and the sequence the NEC expects you to follow.
Service entrance terms (Article 230)
SERVICE = the conductors and equipment connecting the serving utility to the wiring of the premises served. SERVICE DROP = overhead service conductors from the last utility pole to the service point. SERVICE LATERAL = underground service conductors. SERVICE-ENTRANCE CONDUCTORS (overhead OR underground) = from service point to service equipment. SERVICE EQUIPMENT = the main disconnect + overcurrent device. SERVICE POINT = the boundary between utility and customer wiring (often the meter base on residential). NEC 230 governs every component from the utility to the load side of the main breaker.
Reference: NEC 2023 Article 230 + Art. 100 definitions
Standard load calculation — Article 220 Part III
Sequence per 220.40-220.61: (1) GENERAL LIGHTING + RECEPTACLE LOAD per 220.12 (3 VA/sq ft for dwellings); (2) SMALL APPLIANCE + LAUNDRY (1500 VA each x at least 2 small-appliance circuits + 1 laundry); (3) DEMAND FACTOR per Table 220.42 (first 3000 VA at 100%, next 117,000 VA at 35%, remainder at 25% for dwelling); (4) APPLIANCE LOADS per 220.53 (75% demand allowed if 4 or more); (5) DRYER per 220.54; (6) RANGE per Table 220.55; (7) HEATING/AC larger of 220.51; (8) MOTOR loads at 125% of largest plus sum of others. Total VA / 240 V = service amperage.
Reference: NEC 2023 220.40 - 220.61
Optional dwelling-unit calculation — 220.82
Section 220.82 provides an OPTIONAL simplified calculation for one-family or individual unit of two-family/multifamily dwellings served by a 100 A or larger service. Add: (a) 3 VA/sq ft general lighting + receptacles; (b) 1500 VA per small-appliance + laundry circuit; (c) NAMEPLATE rating of all appliances (range, dryer, water heater, dishwasher, etc.); (d) 25% of largest motor. Apply demand: FIRST 10 KVA at 100%, REMAINDER at 40%. Add HVAC (largest of 220.82(C) selections). The optional calc usually produces a SMALLER service size than the standard calc — use it when the dwelling allows.
Reference: NEC 2023 220.82
Worked example — 2,400 sq ft single family
OPTIONAL method: General lighting/receptacle = 2,400 x 3 = 7,200 VA. Two SA + laundry = 3 x 1500 = 4,500 VA. Range nameplate 12,000 VA. Dryer nameplate 5,500 VA. Water heater 4,500 VA. Dishwasher 1,200 VA. Disposal 0.5 HP = ~600 VA. Sum (without HVAC): 35,500 VA. Apply demand: 10,000 at 100% + 25,500 at 40% = 10,000 + 10,200 = 20,200 VA. HVAC (largest): 6 ton AC at ~6,000 VA. Total = 26,200 VA. 26,200 / 240 = 109 A. Round up to next standard service: 125 A panel meets minimum (200 A is more common for resale value + future EVSE/heat pump).
Practice questions (2)
1. Per the optional calculation in 220.82, the demand factor applied to the first 10 kVA of the general load is:
- A.25%
- B.35%
- C.40%
- D.100%✓ correct
220.82(B) applies 100% demand to the first 10 kVA, then 40% to the remainder. The 25% and 35% values are distractors borrowed from Table 220.42 (the STANDARD method demand factors); 40% is the rate applied to the remainder under the optional method, not the first 10 kVA.
2. A single-family dwelling has a calculated load of 95 A. Per 230.79, what is the minimum service-disconnect rating allowed?
- A.60 A
- B.100 A✓ correct
- C.125 A
- D.200 A
230.79(C) sets a 100 A minimum for one-family dwellings, regardless of calculated load. A calc below 100 A does not let you install a 60 A service. 125 A and 200 A are common upgrades but not the code minimum.
02Overcurrent protection + conductor sizing
~90minArticle 240 + 310 — selecting the right wire and the right breaker. Ampacity tables, temperature termination ratings, and the 80% continuous-load rule.
Conductor ampacity — Table 310.16
Table 310.16 gives ampacities for not more than three current-carrying conductors in raceway/cable, in 30°C ambient. Three temperature columns: 60°C, 75°C, 90°C. CRITICAL RULE: even if your conductor is 90°C-rated, you must use the COLUMN MATCHING THE LOWEST-RATED TERMINATION in the circuit. Most circuit breakers and panelboards are 75°C-listed, so for typical residential/commercial circuits you read the 75°C column even with THHN/THWN-2 (which is 90°C-rated). The 90°C column is used for ampacity ADJUSTMENTS (correction factors for ambient temp, conduit fill) before checking termination temp.
Reference: NEC 2023 110.14(C) + Table 310.16
The 80% continuous-load rule
Per 210.20(A) and 215.3, branch circuits and feeders supplying CONTINUOUS LOADS (operating 3 hours or more) must be sized at 125% of continuous load + 100% of non-continuous load. Equivalently: the breaker may load to 80% of its rating with continuous load. Example: a 100 A continuous load requires a feeder + breaker rated 100 / 0.80 = 125 A minimum. The conductor minimum follows the same 125% rule unless the assembly is listed for 100% operation (rare, but exists for some industrial breakers).
Reference: NEC 2023 210.20(A) + 215.3
Adjustment + correction factors
When more than 3 current-carrying conductors are in a raceway/cable, ampacity is adjusted DOWN per Table 310.15(C)(1): 4-6 conductors = 80%, 7-9 = 70%, 10-20 = 50%, 21-30 = 45%, 31-40 = 40%, 41+ = 35%. AMBIENT TEMPERATURE correction is per Table 310.15(B)(1) — for example, in 41-45°C ambient, multiply by 0.87 (75°C column). Apply BOTH factors to the 90°C ampacity (the maximum ampacity allowed by insulation), THEN compare to the 75°C termination column to find the final allowable ampacity. The lower of the two governs.
Reference: NEC 2023 310.15
Practice questions (2)
1. A 75°C-rated breaker terminates a 90°C-rated #6 THHN copper conductor (90°C ampacity = 75 A, 75°C ampacity = 65 A). What ampacity governs at the termination?
- A.75 A
- B.65 A✓ correct
- C.55 A (60°C)
- D.The higher of the two
Per 110.14(C), termination temperature governs. The 75°C breaker forces use of the 75°C column = 65 A — even though the wire insulation tolerates 90°C. The 90°C rating is used for adjustment-factor calculations only, not the final termination ampacity. "Higher of the two" is the most common wrong intuition.
2. A continuous load draws 80 A. Minimum breaker size?
- A.80 A
- B.90 A
- C.100 A✓ correct
- D.125 A
80 x 1.25 = 100 A minimum (210.20(A) for branch / 215.3 for feeder). 80 A would violate the 80% rule. 90 A is not a standard size in 240.6 anyway. 125 A is the next standard size up but is not the minimum required.
03Grounding + bonding (Article 250)
~90minThe most-cited and most-misunderstood NEC article. Grounding electrode systems, equipment grounding conductors, and the bonding jumper that ties them together.
Grounding vs. bonding — definitions matter
GROUNDED = connected to earth or to a conducting body that extends the ground connection. BONDED = connected to establish electrical continuity and conductivity. GROUNDING ELECTRODE CONDUCTOR (GEC) = conductor used to connect the system grounded (neutral) point or equipment to a grounding electrode. EQUIPMENT GROUNDING CONDUCTOR (EGC) = conductive path that provides a ground-fault current path. MAIN BONDING JUMPER = the unspliced conductor/screw/strap connecting the EGC to the grounded conductor inside service equipment — this is where the neutral and ground first touch on the customer side. After the main bonding jumper, neutrals and grounds are SEPARATE — never bonded again on the load side.
Reference: NEC 2023 Article 100 (definitions) + 250.24
Grounding electrode system — 250.50, 250.52
Section 250.50 requires that ALL of the following PRESENT AT A BUILDING be bonded into a Grounding Electrode SYSTEM (per 250.52(A)): (1) metal underground water pipe in direct contact with earth for 10+ ft, (2) effectively grounded metal frame of building, (3) concrete-encased electrode (Ufer) at least 20 ft of #4 bare copper or 1/2" reinforcing rod in concrete contact with earth, (4) ground ring of 20+ ft of #2 bare copper. If NONE of these exist, install one or more of the made electrodes in 250.52(A)(4)-(8): rod/pipe (8 ft minimum, 25 Ω OR augmented with second), plate, or other listed electrode. The water-pipe electrode CANNOT be used alone — must be supplemented (250.53(D)(2)).
Reference: NEC 2023 250.50 - 250.53
EGC sizing — Table 250.122
The Equipment Grounding Conductor is sized per Table 250.122 based on the OVERCURRENT DEVICE rating ahead of the equipment, NOT the conductor size. Examples: 15 A breaker = #14 cu EGC; 20 A = #12; 60 A = #10; 100 A = #8; 200 A = #6; 400 A = #3; 600 A = #1; 800 A = 1/0; 1200 A = 3/0. EXCEPTION: when ungrounded conductors are upsized for voltage drop, the EGC must be PROPORTIONALLY UPSIZED per 250.122(B). EGC need not be larger than the ungrounded conductors. Wire-type EGC is not required where metallic conduit/raceway qualifies as the equipment grounding conductor under 250.118.
Reference: NEC 2023 Table 250.122
Practice questions (2)
1. Per 250.122, an EGC for a 200 A circuit (copper, no upsizing) is sized at:
- A.#10
- B.#8
- C.#6✓ correct
- D.#4
Table 250.122: 200 A overcurrent device → #6 copper EGC. #10 is for 60 A; #8 is for 100 A; #4 is for 300 A. The EGC is sized from the breaker rating, not from conductor ampacity.
2. A house has a metallic underground water pipe (15 ft of contact with earth) and no other electrode. Per 250.53(D)(2), you must:
- A.Use the water pipe alone
- B.Supplement the water pipe with at least one additional electrode✓ correct
- C.Replace the water pipe with a ground rod
- D.Use a 50 ft ground ring
250.53(D)(2) requires the water-pipe electrode to be SUPPLEMENTED by another electrode (typically a ground rod). The water pipe alone is non-compliant due to the risk of the homeowner replacing a section with PVC. Replacement is not required; rings are an option but not the only one.
04Motor branch circuits + sizing
~60minArticle 430 has its own peculiar sizing rules — conductors at 125% of motor FLA, breakers at much higher percentages. Don't apply Article 240 logic blindly.
Motor FLC vs. nameplate FLA
For motor BRANCH-CIRCUIT CONDUCTOR sizing (430.22) and BRANCH-CIRCUIT SHORT-CIRCUIT/GROUND-FAULT PROTECTION sizing (430.52), use the FULL-LOAD CURRENT (FLC) FROM TABLES 430.247-430.250 — NOT the motor nameplate FLA. The tables give "typical" current draws by horsepower + voltage. The nameplate FLA is used ONLY for: motor OVERLOAD (running) protection sizing per 430.32, and for ampacity of separately-supplied control transformers. Mixing these up is the most common motor-circuit calculation error.
Reference: NEC 2023 430.6(A)(1)
Motor branch-circuit conductor — 125% of FLC
Per 430.22, conductors supplying a single continuous-duty motor are sized at 125% of motor FLC (from Table). Multiple motors on one feeder per 430.24: sum of all FLCs PLUS 25% of largest motor FLC. The 25% accounts for the inrush current acceptance, not continuous load — different rule from 210.20(A). A 10 HP 3-phase 230 V motor has a Table FLC of 28 A. Conductor ampacity = 28 x 1.25 = 35 A → #8 cu (75°C col).
Reference: NEC 2023 430.22, 430.24
Branch-circuit OCPD — 250% non-time-delay fuse, 175% inverse-time breaker
Per Table 430.52(C)(1), motor branch-circuit short-circuit + ground-fault protection percentages are MUCH HIGHER than the conductor ampacity — they are sized to allow inrush current. For ordinary (not Design B/C/D, not wound-rotor) motors: NON-TIME-DELAY FUSE = 300% of FLC; TIME-DELAY (DUAL-ELEMENT) FUSE = 175% of FLC; INVERSE-TIME BREAKER = 250% of FLC; INSTANTANEOUS-TRIP BREAKER = 800% of FLC. If the calculated value does not correspond to a standard size in 240.6, you MAY round up to next standard size (430.52(C)(1) Exception 1). Up to 400% is allowed for inverse-time and 225% for time-delay fuse if inrush requires (Exception 2).
Reference: NEC 2023 Table 430.52(C)(1)
Practice questions (2)
1. For sizing the motor branch-circuit conductors, you should use:
- A.The motor nameplate FLA
- B.The full-load current from NEC Tables 430.247-430.250✓ correct
- C.The motor service factor
- D.The locked-rotor current
430.6(A)(1) explicitly directs use of the Table FLC for branch-circuit conductor and OCPD sizing. Nameplate FLA is for OVERLOAD (running) protection — a separate device. Service factor adjusts overload trip points. Locked-rotor current relates to short-circuit calculations, not ampacity.
2. A standard inverse-time circuit breaker for an ordinary AC motor is sized at what percentage of motor FLC per Table 430.52(C)(1)?
- A.125%
- B.175%
- C.250%✓ correct
- D.300%
250% inverse-time breaker. 125% is for conductor ampacity. 175% is the time-delay (dual-element) fuse value. 300% is the non-time-delay fuse value. The breaker percentage allows motor starting inrush without nuisance trips.
External resources
- OfficialNEC NFPA 70 — National Electrical Code (2023 edition) ↗
The code itself. Master exam is open-book on the NEC; tab and highlight before exam day. Articles 100, 110, 210, 220, 230, 240, 250, 310, 314, 408, 430 are responsible for ~80% of master-exam questions.
- OfficialNFPA 70 Handbook (2023) ↗
NFPA-published commentary edition: every article reproduced with explanatory text, illustrations, and worked examples. Not allowed in most exams (handbooks are usually prohibited as too aiding) but the best at-home study companion.
- Third-partyState licensing-board candidate handbook (PSI / Prov / Block) ↗
Each state's candidate handbook lists exam blueprint, allowed reference materials, calculator type, and the business-law portion specific to that jurisdiction. Three biggest national vendors are PSI, Prov, and Block — your state board page tells you which administers your exam.
Last updated: 2026-04-27
We're building this guide right now
Drop your email below and we'll notify you the moment the Master Electrician Exam Prepstudy guide goes live. No spam — one email when it's ready.
